Elizabeth Arcade Student 1

QUEENSLAND

Elizabeth St Brisbane CBD

CLIENT : Student One / El Camino Priority Pty Ltd
OPEN4 SERVICES PROVIDED

Project management, transport, warehousing and installation 

SCOPE OF WORKS

Complete supplier and on-site management of the FF&E installation including receiving & verifying all deliveries at Open4 Brisbane warehouse, delivery to site as required, floor load, placement & assembly.

  • Total of 901 x rooms + 184 x common areas

  • Two towers - Elizabeth St Tower: 23 storeys & Charlotte St Tower: 25 storeys

  • Furniture items = 4,620 items

  • Whitegoods & misc = 1441 items

  • Total volume of product = 2300m3

  • 1900m3 to be received at Open4 warehouse and redelivered to site.

  • 400m3 to be delivered to direct to site by Suppliers

DESCRIPTION / SOLUTION

Where do I start on Open4! What superb FF&E Turnkey installation specialists to have on board to help us kit out our new residential accommodation building for Student One. We worked closely with Open4 for our staged handover new build for well over three months and they were a dream to work with. It was a tricky install with many tight deadlines, stop and start workflows and hard to access areas involved in the staged handover from the builders. This was a piece of cake for Open4 and they worked around the limitations and restrictions extremely well and with a great attitude.

 

Nothing was too much to ask and everything was well managed every day. All staff were well presented and polite and on the ball. To Andrew and the Open4 team – I would like to pass on a sincere thank you from the entire Student One Team. The fit out and opening of our new building couldn’t have gone so smooth without you! If anyone is serious about looking after their FF&E and ensuring the install goes smooth – look no further than Open4. They are the FF&E Turnkey company you are looking for!

TESTIMONIAL


Biggest challenge was the delivery access and time available for trucks to set down goods. It was a Large construction site, One way city street with clearways during peak hours, this meant delivery vehicles had to unload and exit extremely quickly, to do this we palletised all product to ensure quick unload by forklift on site to enable trucks to come and go quickly.